2022 Selective Slab Replacement Project-Area A

The City of Chesterfield plans to perform a slab replacement project on the following streets:

Blackwood Court Bridgeway Drive
Chaistain Court Chesterfield Manor Drive
Cheval Square Drive Crystal Springs Drive
Dejournet Drive Lansbrooke Court
Lansbrooke Drive Lehigh Meadows Court
Meierling Court

All work will be contained within the City’s Right-of-Way.  The work will include complete removal of the existing pavement and the placement of new pavement on the above-mentioned streets.  All sidewalk handicap ramps that intersect with this project will also be replaced to meet all ADA requirements. 

Construction is scheduled to begin in March and substantial completion is expected approximately in October, weather dependent.
 
Emergency services, the United States Postal Service, trash services, and the school district have all been notified of the project and services will not be impacted. 

Two-way traffic will be maintained throughout the project, though some minor delays can be expected. Construction areas can be dangerous for workers and drivers alike. Please use caution while in the work zone for everyone’s safety. 

If you have any questions about the project, please contact Trent Helland at Thelland@Chesterfield.mo.us or at 636-537-4758

PROJECT UPDATES

Punch list items & crack sealing will follow and will be completed by 07-31-2022.

All sidewalks and pavement have been completed as of 07-01-2022.

 07-01-2022 - Phases 1,2,3 and 4 completed on Chesterfield Manor Drive.

06-24-2022 - Phases 1 & 2 completed on Dejournet Drive.

06-07-2022 - Phases 1 & 2 completed on Lansbrooke Drive.

06-17-2022 - Phase 1 completed on Meiering Court.

06-17-2022 - Phase 1 completed on Lansbrooke Court.

06-15-2022 - Phase 1 completed on Dejournet Drive.

06-14-2022 - Phases 1 & 2 completed Lansbrooke Drive.

05-31-2022 - Phases 1 & 2 & 3 completed on Lehigh Meadows.

05-31-2022 - Phases 1 & 2 & 3 completed on Crystal Springs Drive.

05-31-2022 - Phase 1 started on Dejournet Drive.

05-31-2022 - Phases 1 & 2 completed on Chesterfield Manor Drive.

05-23-2022 - Phase 2 started on Lansbrooke Drive.

05-13-2022 - Phases 1 & 2 completed on Cheval Square.

05-06-2022 - Phases 1 & 2 completed on Blackwood Court.

05-06-2022 - Phases 1 & 2 completed on Deveronne Circle.

05-06-2022 - Phases 1 & 2 completed on Bridgeway Drive.

05-06-2022 - Phases 1 & 2 completed on Turnberry Court.

05-05-2022 - Phases 1 & 2 completed on Chaistain Court.

05-04-2022 - Phase 1 started on Lansbrooke Drive.

05-04-2022 - Phase 2 started on Cheval Square Drive.

05-04-2022 - Phase 2 started on Crystal Springs Drive.

05-02-2022 - Phase 2 started on Lehigh Meadows Drive.

04/18/22 - Started Phase 1 on Lehigh Meadows Drive.

04/18/22 - Started Phase 1 on Crystal Springs Drive.

04/18/22 - Started Phase 1 on Cheval Square Drive.

04/14/22 - Started Phase 1 on Deveronne Circle.

04/13/22 - Started Phase 1 on Blackwood Court.

04/08/22 - Started Phase 1 Bridgeway Drive & Turnberry Court.

04/07/22 – Started project on Chastain Court. Phase 1.

03/21/22 - Subdivision meeting for Wildhorse Subdivision.

03/17/22 - Subdivision meeting for Chesterfield Farms.

03/03/22 - Pre-Construction meeting held with contractor.

02/23/22 - Street Slab Replacement Project notices mailed.

02/23/22 - Notice of Award.

02/07/22 - Bid Opening.