2022 Selective Slab Replacement Project-Area B


The City of Chesterfield plans to perform a slab replacement project on the following streets:

Benton Taylor Drive-trench gate Englewood Terrace Drive
Hunters Hill Drive-trench gate Summer Lake Drive
Treherne Court-trench gate
Terrimill Terrace
Sycamore Drive White Elm Court

All work will be contained within the City’s Right-of-Way.  The work will include complete removal of the existing pavement and the placement of new pavement on the above-mentioned streets.  All sidewalk handicap ramps that intersect with this project will also be replaced to meet all ADA requirements. 
 
Construction is scheduled to begin in May and substantial completion is expected approximately in October, weather dependent.
 
Emergency services, the United States Postal Service, trash services, and the school district have all been notified of the project and services will not be impacted. 

Two-way traffic will be maintained throughout the project, though some minor delays can be expected. Construction areas can be dangerous for workers and drivers alike. Please use caution while in the work zone for everyone’s safety. 

If you have any questions about the project, please contact Trent Helland at Thelland@Chesterfield.mo.us or at 636-537-4758

PROJECT UPDATES

07/25/22- Phase 2 starting on Englewood Terrace.

07/25/22- Phase 2 starting on White Elm Court.

07/25/22- Phase 2 starting on Terrimill Terrace.

07/22/22- Phase 1 completed on Englewood Terrace.

07/22/22- Phase 1 completed on White Elm Court.

07/22/22- Phase 1 completed on Terrimill Terrace. 

07/06/22 - Project started on Englewood Terrace and White Elm Court.

07/05/22 - Project is scheduled to start on Englewood Terrace & White Elm Court.  

03/03/22 - Pre-Construction Meeting Held.

02/23/22 - Notice of Award.

02/07/22 - Bid Opening.