Schoettler Road Sidewalk Extension



Schoettler Road Sidewalk Extension

The City of Chesterfield has been awarded a federal grant to construct a 5’ wide sidewalk on the east side of Schoettler Road, between Windsor Valley Court and Greenleaf Valley Drive. An existing retaining wall will also be relocated to the east to make room for the new sidewalk and improve vehicle site distance at that curve. Once complete, the project will fill the last remaining sidewalk gap on Schoettler Road and provide a pedestrian route on at least one side of Schoettler Road from Clayton Road to Chesterfield Parkway, and it will improve pedestrian access to the new Logan Park. Right-of-way acquisition will commence in 2025, and project construction is expected in 2026.

 

STATUS UPDATES

9/26/2024 - Design Consultant is preparing Preliminary Plans.

2/2024
Federal funding for the project was formally allocated in early February. Staff issued a Notice to Proceed to Horner and Shifrin to begin Preliminary Design on the project.


12/2023
An Engineering Services Contract with Horner and Shifrin was approved by City Council.

10/2/2023
Negotiations began for Engineering design services with the engineering design firm deemed to be the most qualified. 

9/21/2023 - RFQ Submittal deadline. Review began on the submittal packages from interested engineering design firms.

8/23/2023 Request for Qualifications (RFQ) was posted to the MoDOT website to request Letters of Interest from qualified civil engineering design firms who would like to be considered for the project design.

 

8/14/2023 - Program Agreement executed between the City and Missouri Department of Transportation (MoDOT).

 

6/8/2023 - Grant formally awarded.

 

8/19/2022 Grant application submitted.